Golden Gate Bridge seismic retrofit to be completed in 6 years

Wednesday, September 30, 2015
GOLDEN GATE BRIDGE (KGO) -- The Golden Gate Bridge District now says seismic retrofit work on its iconic bridge should finally be done by 2021.
[Ads /]
The three stage project began in 1998 and was supposed to cost $300 million. But, our media partner, the Marin Independent Journal, reports the district says rising costs and security upgrades after the 9/11 attacks have tripled the cost to $900 million.

This last phase of work is one factor in the district's projected $213 million deficit. It's also why the district is looking to Washington D.C. for help in paying for the project.